rakeshsehrawat
New member
Goyat Bhai,,,,first thing is that I dont how far the facts you have given below are true. Assuming that these are correct,,,,,then what kind of mentality the drivers of these areas reflect.
What do you think,,,,should these drivers have so much hatred for a particular area,,,,,,
In my oppinion rather than showing this cheap mentality these drivers should praise the kind of work being carried out in Rohtak and because of that the total travel time will decrease and they would be the most happiest people to pass from Rohtak with out getting in to Traffic Jams.
Problem is not only with drivers but at times I have seen the most educated people suffering from the seed of hatreds.
We should come out of that mentality
Gaon Ajaib
Tehsil Meham
Distt. Rohtak
Project:- Renovation of Road from Madina to Ajaib ( Main road connectivity to ajaib from NH-10)Total length 4.3 Km.
Contractor :- Gavad construction Hisar
Total Cost of project:- 117 Lacs + Maintainance for five years for rs. 7.26 lacs
Project Starting Date (in Papers):- 1/03/2009
Actual starting date:- Jan 25 2009 approx
Project finishing date:- 31/08/09
Road width:- 18 feet
Present situation:- All things messed up , Concrete on road , No contractor available.Pictures Shown in same thread
For how long?
Last edited: